Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements...

Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(Sukra Aroon has noticed that the Developers are spending excessive time creating their estimates. He has also observed that the document capturing their assumptions behind these estimates is nearly 20 pages long.

Based on his observation, what advice should he offer to the Developers?)

A.

Ensure that your estimates are accurate enough to support planning but avoid excessive refinement that delays delivery.

B.

Continue refining your estimates as much as possible to eliminate uncertainty, ensuring that all potential risks and complexities are accounted for.

C.

Use broad, high-level estimates only, as attempting to refine estimates beyond this at any stage of the project is unnecessary.

D.

Document every possible assumption in detail, as extensive documentation ensures accuracy and prevents disputes later in the project.

AgilePM-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now AgilePM-Practitioner pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"