The correct answers are A and C .
Aromatherapy oil sales are a new idea outside the original scope , so AgilePM would handle this through collaborative assessment and prioritization , not automatic acceptance or unnecessary bureaucracy.
Why A is correct
“Hold a workshop to assess feasibility and document assumptions.”
This fits AgilePM very well because new ideas should be:
explored collaboratively,
assessed for feasibility and impact,
discussed across business and technical roles,
and understood before being committed.
A workshop is an agile way to bring together the right perspectives quickly.
Why C is correct
“Use MoSCoW prioritization to determine its importance against existing objectives.”
This is also fully aligned with AgilePM. Once the idea is understood, it should be assessed against:
current business goals,
existing priorities,
available time and capacity,
and the likely value it contributes.
MoSCoW is the right mechanism for deciding whether it belongs in the current increment or later.
Why the other options are incorrect
B is too hasty. Alignment with vision alone does not mean the item should be added immediately.
D is too heavyweight for this kind of incremental scope discussion.
E is too dismissive. AgilePM does not say new ideas must always wait until after delivery.
So the best answers are A, C .