APMG-International AgilePM-Practitioner Question Answer
As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
. Heavy rainfall affecting the Wellness Garden.
. Local supplier issues causing material delivery delays.
· Dependency on external contractors for hydrotherapy equipment.
The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the
context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
In addition to the Developers, the teams include:

(Sarah Lark asks Mira Bachar how Spa treatments will remain aligned with the demands of guests post-launch. Mira explained that the Operations Delivery Team will address this in the final Sprint.
Is this approach aligned with AgilePM?)