Comprehensive and Detailed Step-by-Step Explanation
Stakeholder Segmentation in the UniCo Scenario
In stakeholder analysis, external stakeholders are individuals or entities outside the organization but whose involvement is critical for achieving specific outcomes. They contrast with internal stakeholders, who are part of the organization and influence or execute the change.
The relocation of Selco staff to UniCo requires contributions from both internal and external stakeholders, as detailed in the Operational Delivery Processes workstream.
Option Analysis (UniCo-Specific)
A. The staff coordinating user input and working with designers
These staff members are internal stakeholders responsible for ensuring user input and amendments align with organizational needs. They are directly involved with UniCo's design processes, making them part of the internal team.
Incorrect.
B. The UniCo security staff arranging physical access
These security staff are part of UniCo’s internal operations. Their role is critical to operational success but does not classify them as external stakeholders.
Incorrect.
C. The staff communicating the timetable for Selco integration
This group is part of UniCo’s internal change management process, ensuring clear communication during integration. While important, they remain internal stakeholders.
Incorrect.
D. The contracted staff moving furniture and equipment
This group consists of external contractors who are not part of UniCo's workforce but are engaged for specific relocation tasks. Their involvement is temporary and project-specific, aligning them with the external segment of stakeholders.
Correct.
Why D is the Correct Answer (Scenario Alignment)
In the context of UniCo’s relocation workstream, external stakeholders include contractors who facilitate logistical aspects, such as moving furniture. This role is distinct from internal stakeholders responsible for communication or operations.
References (UniCo Scenario and AgilePM Alignment):
UniCo Scenario: The relocation process includes external contractors for moving and setup tasks.
AgilePM Handbook, Chapter 5: Stakeholder Engagement in Change Initiatives.
Agile Business Consortium – Stakeholder Categories and Definitions.