On the seventh day of the Iteration, the team realizes that they will not complete...

On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further. What is the PO's best course of action?

A.

Defer acceptance testing to the next Iteration

B.

Communicate the status of the Iteration to all stakeholders

C.

Have an emergency Iteration Planning meeting

D.

Stop the current Iteration and plan a new Iteration with the new knowledge