What is one result from Iteration Planning for SAFe Scrum Teams?
A.
Iteration demo
B.
Iteration goals
C.
Iteration estimate
D.
Iteration sequencing
The Answer Is:
B
This question includes an explanation.
Explanation:
One of the results from Iteration Planning for SAFe Scrum Teams is the Iteration goals, which are short, specific, and measurable statements that describe what the Agile team intends to accomplish in an Iteration. The Iteration goals are derived from the team backlog, the PI objectives, and the team vision. The Iteration goals help to align the team to a common vision of work in the Iteration, and provide clarity, focus, and motivation. The Iteration goals also enable the team to communicate their progress and dependencies to other teams and stakeholders, and to demonstrate value delivery in the system demo. References: Exam Study Guide: SP (6.0) - SAFe® Practitioner, Iteration Goals
SP-SAFe-Practitioner PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"