What is one element teams present during the draft plan review?
A.
Iteration goals
B.
Planned business value
C.
Milestones
D.
ART PI risks
The Answer Is:
A
This question includes an explanation.
Explanation:
During the draft plan review, teams present their preliminary plans for the upcoming PI, including their iteration goals, capacity and load, and risks and impediments1. Iteration goals are a set of SMART objectives that provide a clear vision and alignment for each iteration2. They also help teams communicate their progress and dependencies to other teams and stakeholders during the PI planning event3. References: PI Planning, Iteration Goals, Presenting PI Planning Draft and Final Plan Reviews