A software company has a portfolio including various types of projects. The projects vary in size, complexity, cost, and other factors. The organization currently follows the Waterfall model of project management and is considering making a transition to Scrum, but is not sure if Scrum can be adopted for all of its projects. As a Scrum Master, which of the following projects would be the BEST candidates for Scrum?
I. Software which has already been developed and new updates are to be released within a fixed time and budget.
II. New innovative software in which there is no guaranteed outcome.
III. A project where skills of developers are unique and are required on multiple projects.
IV. A project where the development team is spread across multiple geographies.