You are the Scrum Master for a power generation project.

You are the Scrum Master for a power generation project. While a Sprint is in progress, the Scrum Team convinces you that the scope of the Sprint has to be changed. You plan to ask the Product Owner to allow additional User Stories to be included in the current Sprint. You remember that “a Sprint cannot be changed once the Sprint begins,” so when can the team's request be considered as an exception?

A.

When the team has exceptionally skilled members who can multitask and help increase the value delivery of the project.

B.

When the team and Scrum Master observe that one member of the team is sitting idle.

C.

When there is a possibility of many Change Requests arising during the next Sprint.

D.

When there is an overestimation of effort during the Sprint, identified by the team and visible in the Sprint Backlog and Sprint Burndown Chart.

SMC PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now SMC pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"