Following are some examples of risks and issues that might be encountered during the course of a Scrum project. Identify which of the following are risks, not issues.
I. After extensive training, marketing representatives might still not be ready to take orders after the project is launched.
II. The painting crew might be delayed due to heavy rain, which could negatively impact the project schedule.
III. Funding was not approved.
IV. Requirements, as currently defined, are unclear.