Which product identifies how often stakeholders require information?
A.
Communication management approach
B.
Quality management approach
C.
Change control approach
D.
Risk management approach
The Answer Is:
A
This question includes an explanation.
Explanation:
The Communication Management Approach in PRINCE2 outlines the means and frequency of communication to stakeholders throughout the project. This document specifies how often stakeholders require updates and information regarding the project's progress and any issues that arise, ensuring that all parties are adequately informed. References: PRINCE2® 7 Foundation Handbook and official training materials.