Which statement about time-driven controls is CORRECT?
A.
Time-driven controls are used for monitoring the progress of work packages and management stages
B.
Time-driven controls take place when specific events happen
C.
Time-driven controls are produced at the end of a stage
D.
An exception report is a time-driven control
The Answer Is:
A
This question includes an explanation.
Explanation:
Time-driven controls in PRINCE2 are mechanisms that take place at predetermined intervals, such as end stage assessments or regular progress meetings, to ensure ongoing monitoring of the project’s progression through its stages and the work being completed in work packages. They help in keeping the project on track by providing timely information on performance. References: PRINCE2® 7 Foundation Handbook and official training materials.
Prince2-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"