To act as a trigger for the 'starting up a project' process
B.
To record the how the project will communicate with its stakeholders
C.
To provide a full and firm foundation for the initiation of a project
D.
To be used by the project board as a basis for reviewing the progress of a project
The Answer Is:
C
This question includes an explanation.
Explanation:
A project brief is produced to provide a full and firm foundation for the initiation of a project. It outlines the project objectives, scope, constraints, and the project management team structure, setting the stage for detailed planning and initiation activities. References: PRINCE2® Foundation Training Manual; PRINCE2® 2017 Foundation handbook.