PRINCE2 PRINCE2-7-Practitioner Question Answer
While preparing the project plan during initiation, the project manager proposes that stage 2 should end at the Council’s financial year-end. This would allow the decision on funding for stage 3 to coincide with the Council’s annual budget process.
Is this an appropriate application of the ‘manage by stages’ principle, and why?