The stage 4 inspections cannot start because a geological survey is late.

The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.

Is this an appropriate approach to leading a successful team, and why?

A.

Yes, because bringing in a replacement subcontractor with the necessary technical skills will enable stage 4 activities to resume and reduce the risk of further delays to the overall project

B.

Yes, because the project manager has the authority to source a subcontractor when an existing team member lacks the technical competence required for their assigned work package

C.

No, because before recommending full team replacement the project manager should first seek to understand the nature of the competency gap and explore support options

D.

No, because the project manager and the survey team manager jointly developed and agreed the terms of the work package, and replacing the team contradicts the co-created ways of working

PRINCE2-7-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PRINCE2-7-Practitioner pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"