While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product...

While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product flow and data from previous projects to determine that the utilities and systems can be delivered in parallel as separate work packages.

Is this an appropriate application of the ‘plans’ practice, and why?

A.

Yes, because data from previous projects should determine the schedule without reviewing the dependencies between the products

B.

Yes, because product dependencies determine sequence, and independent work packages may be planned to run in parallel

C.

No, because work delivered by the same supplier must be scheduled sequentially and should avoid running in parallel

D.

No, because setting work-package tolerances determines the order in which products must be produced

PRINCE2-7-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PRINCE2-7-Practitioner pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"