PRINCE2 PRINCE2-7-Practitioner Question Answer
During stage 2, the design team is developing measures to minimize disruption to residents and local businesses. To build a relationship with this large external stakeholder group, the Sustainability Manager arranges a monthly newspaper article explaining the measures and inviting feedback.
Which PRINCE2 Project Management principle is MOST directly demonstrated, and why?