During stage 2, the design team is developing measures to minimize disruption to residents and...

During stage 2, the design team is developing measures to minimize disruption to residents and local businesses. To build a relationship with this large external stakeholder group, the Sustainability Manager arranges a monthly newspaper article explaining the measures and inviting feedback.

Which PRINCE2 Project Management principle is MOST directly demonstrated, and why?

A.

Define roles, responsibilities and relationships, because the project is actively engaging and communicating with an external stakeholder group

B.

Define roles, responsibilities and relationships, because the Sustainability Manager must be the sole spokesperson for every project communication

C.

Tailor to suit the project, because every large project is required to communicate through a local newspaper

D.

Tailor to suit the project, because the Portfolio Director is personally accountable for preparing all stakeholder communications

PRINCE2-7-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PRINCE2-7-Practitioner pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"