The correct mapping is Item 1 — B; Item 2 — F; Item 3 — C .
Item 1 belongs under planning assumptions and prerequisites. The plan is being constructed on the assumption that limited experience with sustainable technologies increases the possibility of design errors and consequently requires additional quality-control time. This is a planning assumption that affects how the stage is estimated and scheduled.
Item 2 belongs under monitoring, control and reporting arrangements. Sending a design-progress summary to the project board every two weeks defines the frequency and mechanism by which progress information will be communicated and controlled during the stage.
Item 3 belongs under products to be delivered. The architectural visualizations are explicit outputs that stage 2 is expected to create. They are therefore part of the defined product scope of the stage plan.
The other headings address different planning information. Dependencies identify relationships that constrain sequencing; budget records the financial resources authorized for the plan; and tolerances establish permissible deviations from performance targets before escalation becomes necessary.
The question demonstrates that a PRINCE2 plan is not simply a schedule. It integrates products, assumptions, resources, controls, tolerances, dependencies, and reporting arrangements into a coherent management product.
PRINCE2 7 reference topics: Plans practice; stage plan; planning assumptions; products; monitoring and control arrangements; product-based planning.
===============