You work as a project manager for BlueWell Inc.

You work as a project manager for BlueWell Inc. By referring to the figure given below, you along with your project team is calculating the latest completion of an activity.

What is the latest your project team can complete Activity I?

A.

Day 29

B.

Day 26

C.

Day 25

D.

Day 30