Harry works as a project manager for BlueWell Inc.

Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an input to the determine budget process?

A.

Contract

B.

Reserve analysis

C.

Scope baseline

D.

Project schedule