You work as a project manager for BlueWell Inc.

You work as a project manager for BlueWell Inc. Management has asked you to communicate with them whenever your project is about to reach a milestone so that they can review your project performance to date. Where can you find a list of the project milestones to anticipate management's request?

A.

Scope baseline

B.

Milestone list

C.

Project charter

D.

Project Schedule Management Plan