A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?

A.

Work breakdown structure

B.

Requirements management plan

C.

Use cases

D.

Traceability matrix