A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements...

A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.

What is the most effective way to manage this situation?

A.

Discuss the change with stakeholders during the baseline approval meeting and ask them to approve the new baseline.

B.

Ask for more resources to manage this change and justify these additional resources with the value the change will give to

the company.

C.

Share the new requirements with all stakeholders and ask them to submit their comments before the meeting.

D.

Postpone the baseline approval meeting, analyze the impact, and schedule a new meeting to discuss dependencies and

priorities with stakeholders.

PMI-PBA PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-PBA pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"