Midway through the requirements gathering phase, a stakeholder informs the business analyst that a requested...

Midway through the requirements gathering phase, a stakeholder informs the business analyst that a requested requirement does not address the solution. The stakeholder wants to know who made the request. The business analyst spends hours searching emails to identify the requestor.

What should the business analyst have documented?

A.

Sponsor approval in the requirements traceability matrix

B.

The source in the RACI matrix

C.

Roles and responsibilities in the RACI matrix

D.

The source in the requirements traceability matrix