The story should be assigned eight story points as per the majority vote
B.
The story should be added to the backlog and reassessed later
C.
The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached
D.
The decision for the number of story points should be made by the customer
The Answer Is:
C
This question includes an explanation.
Explanation:
Story point estimation in agile is acollaborative team activity, and consensus is critical. Techniques likePlanning Pokerare designed to reveal differences in understanding. According to thePMI Agile Practice Guide (Section 5.2 Estimating Techniques)andMike Griffiths (Chapter 6: Adaptive Planning), when there's adiscrepancy in estimates, it is essential todiscuss and understand the rationalebehind differing views.
Option Cis correct: the team shoulddiscuss and clarifyto reach a shared understanding.
Option Aignores potential misunderstandings.
Option Bunnecessarily delays estimation.
Option Dis incorrect—the team, not the customer, estimates the effort.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"