A scrum team is working together virtually.

A scrum team is working together virtually. One of the team members sends a daily email to the other team members listing impediments that they find. During retrospective meetings, the team member complains that their colleagues fail to take actions on the impediments.

How should the team address this issue?

A.

The team member that is complaining should talk individually with the scrum master to remove impediments.

B.

They should ask for more details about the impediments and then resolve them when the team has more time to investigate.

C.

The team member that is complaining should address the impediments in daily scrum, communicating them directly.

D.

Team members should state that they need to prioritize their work instead of responding to daily emails about impediments.

PMI-200 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-200 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"