An organization is using a predictive approach to managing projects.

An organization is using a predictive approach to managing projects. The executives like to see more deliverables in a short time and require that the milestones be achieved on time.

What value can the organization gain by moving to an iterative approach?

A.

New tools that deliver iterative and incremental work

B.

A more predictable delivery schedule and better quality

C.

Higher levels of activity-based planning and user histories

D.

Increased focus on the value and benefits delivered