The product owner is present at the sprint review meeting and states that an estimation...

The product owner is present at the sprint review meeting and states that an estimation for the end of the project must be shared with the company’s steering committee. The scrum master declares that the team reached an average velocity of 40 story points per sprint, considering a biweekly iteration. The team members predict that there are 240 story points remaining.

What is the estimated project conclusion?

A.

Twelve months

B.

Three months

C.

Six months

D.

Two months