New Year Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac75sure

Which of the following correctly states the relationship between urgency, priority and impact?

Which of the following correctly states the relationship between urgency, priority and impact?

A.

Impact, priority and urgency are independent of each other

B.

Urgency should be based on impact and priority

C.

Impact should be based on urgency and priority

D.

Priority should be based on impact and urgency

ITIL-F PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now ITIL-F pdf
Get 75% Discount on All Products, Use Coupon: "ac75sure"