ISM CORE Question Answer
FGH, Inc. has purchased components from Supplier A for many years. The supplier's performance has been very good, with reliable deliveries and consistently high quality. As contract renewal approaches, Supplier A informs FGH's supply manager that a significant price increase is anticipated, based primarily on the costs of building a new production facility. The supply manager has been directed to negotiate a new contract with Supplier A only if it agrees to maintain current pricing. Which of the following is the BEST way for the supply manager to prepare for negotiations with Supplier A?