ISM CORE Question Answer
A supply manager Is evaluating bids for a new delivery van. Supplier J, which has provided similar equipment in the past, quotes a price of $50,000. Supplier K quotes a price of $52,500, but Includes an offer to buy back the van at the end of five years for $3,000. Both suppliers' bids meet specifications and delivery requirements. At a 10% opportunity cost of capital, and with the 5-year present value of $1 at $.62, which supplier should the supply manager choose, and why?