Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements...

Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(The Developers have used the Planning Poker technique to generate their estimates. Hira now needs to determine how many Sprints will be required for the Delivery Teams to deliver the Eco-spa.

What should the Developers do to help Hira make this decision?)

A.

They should use the commitment-based planning technique to estimate how many story points of work can be achieved in a Sprint.

B.

They should convert story points to person days, allowing Hira to establish how many Sprints will be needed based on development capacity.

C.

They should assign average time allocations for each backlog item, making it easy for Hira to ensure that every Sprint has an equal workload.

D.

They should re-estimate using a more appropriate technique because Story Point estimating intentionally avoids associating time with effort.

AgilePM-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now AgilePM-Practitioner pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"