The PI Planning process is a two-day event that aligns all the teams on the Agile Release Train (ART) to a shared mission and vision for the upcoming Program Increment (PI)1. The PI Planning process has several inputs and outputs, as shown in Figure 12. One of the outputs of the PI Planning process is the PI Objectives, which are a set of SMART (Specific, Measurable, Achievable, Realistic, and Time-bound) goals that each team and the ART commit to achieving in the PI3. The PI Objectives are based on the features and enablers that the teams plan to deliver, and they reflect the business and technical value that the teams and the ART intend to provide to the stakeholders4. The PI Objectives are also used to track the progress and performance of the teams and the ART throughout the PI execution5. The other options are not outputs of the PI Planning process, but rather inputs or outcomes. The PI Vision is an input to the PI Planning process, which describes the current state, future state, and features of the solution that the ART will deliver in the PI. The PI Goals are an outcome of the PI Planning process, which are derived from the PI Objectives and summarize the business and technical benefits that the ART will deliver in the PI. The Actual PI Business Value is an outcome of the PI execution, which measures the actual value delivered by the ART at the end of the PI, based on the PI Objectives and stakeholder feedback. References: PI Planning - Scaled Agile Framework, Inputs and Outputs of PI Planning - Scaled Agile Framework, PI Objectives - Scaled Agile Framework, PI Planning - Scaled Agile Framework, Program Execution - Scaled Agile Framework, [PI Vision - Scaled Agile Framework], [PI Goals - Scaled Agile Framework], [Inspect and Adapt - Scaled Agile Framework]
Figure 1. Inputs and outputs of PI Planning2