What are the three key items communicated on the Program Board? (Choose three.)
A.
Feature delivery dates
B.
PI Objectives
C.
Program risks
D.
Milestones
E.
Dependencies between teams
F.
Team velocity
The Answer Is:
A, D, E
This question includes an explanation.
Explanation:
The Program Board is a visual summary of the Program Increment (PI) planning outputs and is used to communicate key aspects of the plan to stakeholders. According to the SAFe framework, the three key items communicated on the Program Board are:
Feature delivery dates: These indicate when features are planned to be delivered within the PI.
Milestones: These are significant events or achievements that are critical to the program’s progress and are used to track alignment and progress toward the PI objectives.
Dependencies between teams: These show the relationships and interdependencies between different teams that need to be managed and coordinated to ensure smooth delivery of features.
These items are essential for creating transparency and alignment across teams and stakeholders, helping to manage risks, and facilitating the resolution of dependencies1. The Program Board helps in visualizing the work and aids in the coordination of the ART’s efforts during the PI2.
SAFe-RTE PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"