Who is responsible for managing the progress of work during a Sprint?
A.
The Scrum Master.
B.
The Development Team.
C.
The Product Owner.
D.
The most junior member of the Team.
The Answer Is:
B
This question includes an explanation.
Explanation:
The correct answer is B, because the Development Team is responsible for managing the progress of work during a Sprint. The Scrum Guide states that “the Development Team tracks this total work remaining at least for every Daily Scrum to project the likelihood of achieving the Sprint Goal. By tracking the remaining work throughout the Sprint, the Development Team can manage its progress.”