Who determines how many Product Backlog items the Developers select tor a sprint?

Who determines how many Product Backlog items the Developers select tor a sprint? (choose the best answer)

A.

The Scrum Master

B.

The Scrum Team

C.

The Developers

D.

The stakeholders attending Sprint Planning

E.

The Product Owner