To decide which project approach is suitable for the project
B.
To fully understand how the project objectives will be achieved before committing significant resources
C.
To produce the required Work Packages
D.
To enable corporate or programme management to give authorization to deliver a project
The Answer Is:
B
This question includes an explanation.
Explanation:
The Initiating a Project process is used in PRINCE2 to ensure that there is a thorough understanding of how the project's objectives will be achieved, which includes a definition of the project's scope, benefits, risks, and approach before significant resources are committed. This process helps in establishing a clear and shared understanding of the project's basis before moving forward. References: PRINCE2 Foundation manual, PRINCE2 official resources
Prince2-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"