Define the period over which the cost-benefit analysis will be based
B.
Describe how to measure the performance of the project's products in operational use
C.
Define the scope, timing and ownership of the benefit reviews required
D.
Describe how to measure and confirm any benefits that are to be realised after the project is closed
The Answer Is:
A
This question includes an explanation.
Explanation:
The Benefits Review Plan in PRINCE2® does not typically involve defining the period over which the cost-benefit analysis will be based. Its main purposes are to describe how and when the benefits of the project will be measured, including the scope, timing, and responsibility for the benefit reviews post-project closure. References: PRINCE2® Foundation official guide and study material.
Prince2-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"