When should the project baseline be updated in order ta meet the purpose of the...

When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?

A.

When a request for change is recorded on the issue register

B.

When a business opportunity has been recognized

C.

When the project manager receives a request for change

D.

When a change has been approved by the change authority