Which statement about the 'manage by stages’ principle is CORRECT?
A.
The project board should authorize multiple stages at the same time
B.
The end of a stage should provide a control point for the project board
C.
A project should have fewer, longer stages when the risk exposure is high
D.
A project should have separate stages to plan, deliver and close the project
The Answer Is:
B
This question includes an explanation.
Explanation:
The 'manage by stages' principle in PRINCE2 dictates that the end of each stage provides a control point at which the project board can review progress, reassess project viability, and decide on the next steps. This approach allows for regular monitoring and decision-making, ensuring that the project remains aligned with its objectives and within its tolerances.References: PRINCE2® 7 Foundation guide on the 'manage by stages' principle.
Prince2-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"