A risk budget may fund the implementation of a fallback plan, which is activated if a risk materializes. This ensures that resources are available to manage and mitigate the impact of risks on the project, aligning with proactive risk management strategies in PRINCE2. References: PRINCE2® 7 Foundation Handbook and official training materials.