What is a supplier of a PRINCE2 project responsible for?
A.
Providing the project mandate
B.
Providing resources to deliver the project outputs
C.
Establishing the project's governance
D.
Realizing the benefits from the project
The Answer Is:
B
This question includes an explanation.
Explanation:
In PRINCE2, the supplier is responsible for providing the resources necessary for delivering the project outputs. This includes supplying the skills, materials, and technologies required to produce the products of the project, ensuring that these resources meet the project's specifications and quality requirements. References: PRINCE2® 7 Foundation Handbook and official training materials.