The correct mapping is Item 1 — A; Item 2 — E; Item 3 — E .
Item 1 belongs in the risk register. The cracked pane itself is an existing problem and therefore an issue. However, the item explicitly identifies a separate uncertainty : the supplier may fail to meet the future replacement date, potentially delaying later work. Because this is an uncertain future event affecting project objectives, it is a risk and should be recorded in the risk register.
Item 2 belongs in the risk management approach. It describes the agreed procedure and frequency for reviewing project risks. The risk management approach defines how risk management will be performed, including responsibilities, procedures, review arrangements, scales, reporting, and supporting techniques.
Item 3 also belongs in the risk management approach. A red-amber-green classification is part of the project’s agreed risk assessment and prioritization framework rather than information about an individual risk.
The distinction is fundamental: the risk register contains individual identified risks and their management information , whereas the risk management approach defines the project’s overall method, procedures, scales, responsibilities, and controls for managing risk .
PRINCE2 7 reference topics: Risk practice; risk register; risk management approach; uncertainty; risk assessment; risk review arrangements; risk scales.
===============