At the start of stage 3, the project board inserts detailed recycling tolerances directly into...

At the start of stage 3, the project board inserts detailed recycling tolerances directly into each work package without the project manager agreeing the delegated targets with the relevant team managers.

Is this an appropriate application of the progress practice, and why?

A.

Yes, because team managers generally need to comply with sustainability metrics set directly by the project board

B.

Yes, because the project board should collect and review work-package progress directly from each delivery team

C.

No, because the project manager should authorize the work packages and agree the delegated sustainability tolerances

D.

No, because sustainability tolerances should be recorded only at project level rather than delegated through work packages

PRINCE2-7-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PRINCE2-7-Practitioner pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"