Before accepting the stage 2 design work package, the BuildyBrick team manager needs to determine...

Before accepting the stage 2 design work package, the BuildyBrick team manager needs to determine how the design team will be organized and controlled and whether the work can be achieved within the stated constraints.

During which ‘managing product delivery’ activity should this be done?

A.

Notify work package completion

B.

Execute a work package

C.

Evaluate a work package

D.

Accept a work package