The correct answer is D — Accept a work package . The first activity in the managing product delivery process ensures that the team manager fully understands the proposed work package and determines that it can realistically be delivered before accepting responsibility for it.
The BuildyBrick team manager therefore needs to examine the required products, product descriptions, constraints, tolerances, interfaces, quality requirements, reporting arrangements, available resources, and relevant issues and risks. The team manager also determines how the specialist team will be organized and controlled and, where appropriate, develops or confirms the team plan. Any concerns about achievability should be discussed with the project manager before acceptance rather than discovered after work has begun.
Option B occurs after the work package has been accepted and covers development of the products, performance of quality activities, management of delivery, and handling of issues and risks during execution. Option C occurs periodically during delivery to evaluate progress and status against the work package and team plan, including preparation of checkpoint information. Option A occurs at the end, once completed products and required approvals are ready to be handed back to the project manager.
Therefore, confirming that the work is achievable within its stated constraints is an essential part of accepting the work package .
PRINCE2 7 reference topics: Managing product delivery; accept a work package; team manager; work package constraints; team planning; Ref. 17.4.1.
===============