True or False: You shouldn’t start planning for the end of a project until the end is in sight.
A.
True
B.
False
The Answer Is:
B
This question includes an explanation.
Explanation:
Planning for the end of a project should begin from the project’s inception. This is because effective project management involves understanding and planning for the project lifecycle, which includes closure. The closure phase is critical for ensuring that all project work is completed, objectives are met, and the project is formally closed out. It is also important for capturing lessons learned and releasing project resources1234. References: Professional in Project Management (PPM) Reference Materials1234.