Which of the following tasks does not take place during the first phase of a project?
A.
Determining feasibility
B.
Developing basic budgets and schedules
C.
Obtaining resources (such as time and money)
D.
Naming the starting project team]
The Answer Is:
D
This question includes an explanation.
Explanation:
During the first phase of a project, which is the initiation phase, the focus is on defining the project at a broad level. Key activities include developing a project charter, identifying stakeholders, and determining the project’s feasibility. The initiation phase is about giving the project a structure, not about the detailed planning of resources or scheduling, which occurs in the subsequent planning phase. Therefore, naming the starting project team is not typically part of the initiation phase.
References: The information is based on the standards and guidelines provided by the Project Management Institute (PMI) in the PMBOK Guide and the Professional in Project Management (PPM) certification materials12.
PPM-001 PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"