A ___________ can help you identify the biggest priorities in your project.
A.
Gantt chart
B.
Statement of Work
C.
Target chart
D.
Pie Chart
The Answer Is:
A
This question includes an explanation.
Explanation:
A Gantt chart is a project management tool that provides a visual representation of a project schedule, allowing project managers to see the duration of activities, their start and end dates, and dependencies between tasks. This visualization helps in identifying the most critical tasks that could impact the project timeline and thus assists in prioritizing the project’s biggest priorities.
References: The information is aligned with the PMBOK® Guide and other PPM reference materials, which describe the use of Gantt charts in project time management and prioritization1.
A Gantt chart is a powerful project management tool that can help identify the biggest priorities in a project. It visually represents the project schedule, showing the start and end dates of individual tasks and their dependencies. By laying out the timeline and workload, a Gantt chart makes it easier to see which tasks are critical to the project's timeline (often referred to as the critical path) and therefore should be prioritized.
PPM-001 PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"