Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

When reviewing the project team's performance the project manager realizes that the team velocity is...

When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?

A.

Increase the sprint duration to allow the team more time

B.

Prioritize the contents of the backlog and remove some stories

C.

Create a change request to modify the gate review goals

D.

Use the standup meeting to assess impediments and problems

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"