PMI PMP Question Answer
Having managed a similar project while working with previous stakeholders, a
project team decided to use the same report format they used in the earlier project.
However, stakeholders new to the project are not fully comprehending the status of the
project based on the reports that are being circulated.
How should the project manager address this concern moving forward?